Village of Monticello to Proceed with Referendum on April Ballot
January 25, 2018
The Monticello Village Board met for its regular meeting on Wednesday, January 17, 2018.
Bart Nies of Delta 3 Engineering appeared before the board to discuss the plans for the Kennedy Lift Station, and the Waste Water Treatment plant upgrades.
Nies said that if the board approved the sending out of bids, that a completion date of July 3, 2018 was possible. He reminded the board that in September of 2017 he had given them a rough estimate of $240,000 for the project. Though it is still a rough estimate, Nies noted that he believed it could come in at approximately $220,000. But he cautio...